38BU1423Little Huspa Creek: seasonal occupation across multiple periods
What the study found
The 2006 Phase II/Phase III management summary described predominantly Woodland-period seasonal occupation, with minor Late Archaic and Yamassee-era visitation. Investigators recorded artifact-pattern and feature evidence including hearths and oyster-processing features.
Management outcome
SHPO found the management summary acceptable, consistent with the MOA and data-recovery plan, and stated that ground disturbance in the mitigated area could proceed while the draft/final reporting process continued.
Project record: Barr & Associates, Management Summary of a Phase II Cultural Resources Survey, Inventory and Assessment and a Phase III Data Recovery of Site 38BU1423 (final Oct. 3, 2006); SHPO correspondence (July 19 and Oct. 2006).
38BU1424Lot 44: Yamassee occupation associated with Huspa Town
What the study found
Brockington described archaeological deposits associated with a Yamassee occupation believed to be part of Huspa Town. SHPO had determined the site eligible for the National Register of Historic Places.
Management outcome
SHPO's 2005 letter found the revised management summary followed the MOA and treatment plan and allowed permitting within the mitigated area to proceed. A 2019 completion proposal called for artifact analysis, ethnobotanical study, agency-reviewed reporting and permanent curation, while permitting limited retention for responsible exhibits.
Project record: SHPO, Revised Management Summary acceptance (Apr. 29, 2005); Brockington and Associates, Completing Archaeological Data Recovery Investigations at 38BU1424 (Apr. 2, 2019).
38BU1426Phase III data recovery and public-information commitments
What the study found
The site was treated under the Bull Point Development Tract MOA signed in November 1995. The submitted management summary documented implementation of the accepted fieldwork component of the data-recovery plan.
Management outcome
In February 2008 SHPO stated the fieldwork had been satisfactorily implemented, analysis and reporting were underway, and it did not object to land-disturbing activity at the site location. SHPO also requested the draft technical report and public-information plan.
Project record: R.S. Webb & Associates, Phase III Data Recovery Excavations at Site 38BU1426 management summary (Nov. 3, 2007); SHPO acceptance correspondence (Feb. 4, 2008).